Demolition/ Pavers/ Granite/ Bamboo
Customer: Edward Kornuszko
Address: 7056 Lanier Falls Rd. (DeLand, FL)
Crew:
(LF) Eric Moore
(CM) Josh Webster
Sub Contractor: SMR Pavers (Silvano)
SCOPE:
Refer to PBR below for scheduling and scope of work.
Nathan to handle procurement for project materials.
Tuesday: (5.30.23)
7:45 am: Stop by Site one and Collect:
Jason: Timer
Rick & Jackie Timer
8:30 am: Drop off pavers & unload with Josh on site & Site walk with Josh.
9: 30 am: Josh to stay on site during pickups and complete following:
Dripline installation completion
Bamboo plant (1) Installation
Rake Grass/ Grade by paver lips and prep areas for sod designated by Nathan.
Clean Up Site and prep for pine nugget install.
9:45 am- 11:00 am: Nathan (Procurement)
Pick Up Half Pallet of Sod (R&R)
3 yd pine bark (Volusia Shed)
11:00 am-11:15 am: Arrive back on site:
Complete Paver Installations with Josh (16x16 Harvest Blend on Paver Base)
Install 3 yd. pine bark
Josh Pressure wash driveway while Nathan adjust beds and tamps center line of grass down to alleviate ruts.
4:00 pm: Perform Site walk with Edward and Watney
Bounce out
Equipment:
V10, U-Dump
(2) Wheel Barrel *On site
Pressure Washer
Backpack Blower