Back to All Events

David Schroeder


 

Demo/ Irrigation/ Installs/ Mulch - EVOLVING

Customer: David Schroeder (Stratton Project)

Address: 1010 Lake Diaz Cemetery Road (DeLeon Springs, FL)

Crew:

  • (DM) Eric Moore

  • (CM) Colby Keith

  • (CM) Christian Myers

SCOPE:

(Prep) DAY 1

  • Removal of all plants, sod, and mulch as signified on landscape plan. within the Phase 1 specs.

    • Level beds for planting -Dump fees associated

  • *Leave Bird of paradise and Sago palm that is closest to front door (see landscape plan)

(Irrigation) - Stock/ Site One

  • Pop up shrub heads with NP rotator nozzles to irrigate plants installed in phase 1 -Includes timer adjustment and inspection 1 month after install (on schedule for August 10 performed by Nathan)

(Drainage) - Site One (Orange City)

  • Drainage ran for 4 downspouts

  • (2) on north side of walkway ran out of bed

  • (2) on south side of walkway ran under sidewalk into yard

    • 1 roll SOLID 4' corrugated

    • 4 DS adapters

    • 4 pop up emitters

Second half of this project is on hold due to weed treatment that needs to take place before plantings

(Plant install) Day 2 - TBD currently on hold until Treatment is completed

  • Installation and materials for all plants outlined for phase 1 package below

(Mulch) - West Volusia Shed on Hold

  • Installation of 16.5 yds brown shredded

(Delivery) - TBD

  • Pick up of plants and materials

(Notes)

  • Stratton

Equipment:

  • V10, Sure Trac with rails

  • Mini Skid

  • Backpack Blower

  • Stakes (Purchase 2 boxes if needed)