7 Brew Landscape Construction
Project: 7 Brew Coffee
Customer: 7 Brew Coffee
Address:1940 S 14th Street (Fernandina Beach, FL)
Landscape Design Team: RNR Construction
Architecht: A&K Land Planning & Design
(904) 476-9692
Project Manager: Edward (RNR Construction)
(732) 674-4854
Sub-contractor: McBride Land Services
B2B/ Admin: Camren McBride
Logistics Ops Manager: Nathan Cabral
Project Manager: Eric Moore
Foreman: Josh Webster
McBride Subs: CIS (Central Irrigation Specialists)
Demetrio Martinez
(386) 748-4507
Sub Contractor Etiquette
NO Cursing/ Foul Lanuage: Day Care, we will need each others help on this one just check each other if it happens so were being curtious.
No smoking or vaping on the premises
Take Breaks Off Premises
Keep Tools Off Finished Surfaces
No Loud Music
Observe Start and Stop Times
Leave it the Way You Found it
Dress Like a Professional
Hydrate!Customer: 7 Brew
Project Details
Address: 1940 South 14th Street (Fernandina Beach, FL)
Crew:
(DM) Eric Moore
(FM) Joshua Webster
Sub: Demetrio (CIS)
SCOPE:
Day 1:
-6:30 am departure to Fernandina Beach
Camren: Dovetail & Big Skid
Eric & Josh: V10/ U-Dump & Mini Skid (With Rails)
After arrival on site:
Walk facilities with cam to discuss any further questions once eyes are on the project.
Set up protective fencing barrier around all protected trees, not to impede demolition areas.
Begin demolition within irrigation areas to prep for demetrio to lay valves, backflow and main lines on Friday.
Day Two (Showtime: 7:00 am)
Continue demo in all irrigation areas to mitigate damage to any installed lines. Demetrios crew will be back on site the following week to install drip lines.
Demo of all beds to run for the next two days.
If your starts getting full call Nathan to coordinate swap out of dumpster.
Day Four: TBD
Logistics & Equipment List Attached Below
Plants and Lodging Images Below
Deployment Lodging (Days INN) Kingsland, GA
Project Plants (Total: 554)