Sunrise Elementary

 

Site Clean Up

Customer: Daniel Hickey (GC) Sunrise Elementary School

Address: 3155 Phonetia Dr. (Deltona, FL)

Crew:

  • (P) Camren McBride

  • (FM) Ethan Yorio

  • (CM) Alex Caban

  • (DM) Eric Moore (IR)

SCOPE:

(Prep)

Remove all existing plants in:

  • (3) raised beds

  • (2) octagon and flag pole bed

    • Most removal in beds are by hand due to machine not having reach into the center.

(Plant installs)

  • (100) 1 gallon Asiatic jasmine

    • (40) in each of the octagon beds

    • (20) in the flagpole bed.

  • (2) 3 gallon Firebush in the centers of the octagon beds.

  • (2) 3 gallon Pink Muhly grass in either corner of flagpole bed Plants above

    • *3 gallon are installed with soil and slow release fertilizer.

(Mulch)

  • Install (6) yards of brown shredded mulch

(Delivery)

  • Locate and deliver all plants/material to jobsite

(Sod)

  • Removal of juniper, Ligustrum and sod in areas near drop off/fire hydrant

  • Sod install to follow (4) pallets of Bahia. to be picked up by Camren on Friday with dovetail and Big Skid and delivered to site.

Equipment:

  • V10, Mini Skid Sure Trac with rails

  • Cam Full Size Skid and dovetail for deliveries

  • Backpack Blower

  • Wheel Barrels

  • Irrigation Boxes