Back to All Events

Cathy Atwood


 

Swale Grading, Jute Mat, Sod Install

PROJECT APPROVED

We Are the Subcontractor on this site, please be curious/ mindful and uphold professionalism.

Customer: Cathy Atwood (1625) New Customer

Phone: (727) 504-1485

Address: 1451 Hallelujah Way (Sanford, FL)

Crew: DAY 1 (Prep Day)

  • (LF2) Bob Nichols - Procurement

  • (LF2) Ethan Yorio- Field Project Manager

  • (MF) Eric Moore

Crew: DAY 2 & 3 (Install Day)

  • (LF2) Ethan Yorio- Field Project Manager

  • (MF) Eric Moore

  • (FM) Josh Webster

  • (CM2) Jonathan Howell

SCOPE:

Notes:

  • Bring a handheld Sump Pump and discharge hose, it rained over the weekend which may have caused the existing swale to fill up a bit.

(Grade Work)

  • Re grade swale to cleanup existing erosion and ensure steady slope from road to back ditch (Erosion control) Refer to site plan for direction. Back of swale near aft most tree to be the lowest point of the slope of the swale to be graded,

(Sod)

  • Install (4) rolls of 4x250 ft Jute matt on both slopes sides of swale to mitigate future erosion

  • Install (25) pallets of Bahia sod along swale on northern side of property

  • Install sod on top of Jute Mat after mat has been installed

  • Sod to be delivered to site Tuesday Jan 9 Between 8:00 am - 12:00 pm from Hillside Farms

Equipment:

  • 7.3L

  • Big-Skid

  • Laser Level

  • Irrigation Boxes

Previous
Previous
December 20

Sarah McKaskill (Nate)

Next
Next
January 8

Kelly Linz