Objectives Week 4:

  • Boulder, Rock, Stone Pick Ups

  • Boulder, Rock, Stone Installations

  • Sand Installations

  • Top Soil Installations

  • Burn/ Spray Weeds & Grass growing back within facility.

  • Final Log Placements

    • Dig Table in infant area down no less than 18” above grade.

  • Climbing Wall and Kitchen placement

  • Plant Installation

  • Drainage Inlet Covers and Outlet Covers

  • Sod Installation

  • Manilla Rope installation

    • 1/2” delivered to Heathers house.

      • Add one post to NE corner of playground at fence line

      • You will need another bracket and tapcons to install into concrete.

(Monday) 4.10.23

7:00 am Departure to Smokey Valley | 8:30 Departure to Lutz, FL

o   Eric & Josh: V10 (U-Dump, Rails, Mini-Skid)

  • Bring 4 Bags on Concrete from Cams truck*

  • Bring Weed Mat Roll

8:00 AM- Pick Up Smokey Valley (Sanford)

  • (1) Pallet Blue Tumbled

    • Order: 2.06 Tons= $1139.57

 

Cam: SureTrac (Boulders, Flagstone, Rock)

Budget: $2,600 shared with Winter Garden Stone Budget &3500 total

Pebble Junction (Flagstone)

  • Tumbled Stone, Loose Boulders

  • Cost: 400.54/ ton

  • Order: 2.18 Tons= $975

Smokey Valley (Steppers)

  • (1) Pallet Thick Stepper

  • Cost: 400.54/ ton

  • Order: 2.11 Tons= $924.18

12:00 PM Lutz Arrival (Eric & Josh)

o   Offload Mini Skid and Pallet using Kubota

o   Pick Up Sand from Big Earth and Fill Both Sandboxes using Mini Skid.

o   (CuYd. Measurement on site by Eric.)

Once sand install is complete install Chalk Board and Art Board in Orange Flagged spots

Project: Nest Playground Enhancement

Customer: The Nest Schools

Landscape Design Team: Evolving Landscapes

  • Architecht: David Schroeder “Evolving Landscapes”

  • Project Manager: Heather Bass “Evolving Landscapes”

Sub-contractor: McBride Land Services

  • Project Manager: Camren McBride

  • Ops Manager: Nathan Cabral

  • Lead: Eric Moore

  • Crewman: Josh Webster

Sub Contractor Etiquette

  • NO Cursing/ Foul Lanuage: Day Care, we will need each others help on this one just check each other if it happens so were being curtious.

  • No smoking or vaping on the premises

  • Take Breaks Off Premises

  • Keep Tools Off Finished Surfaces

  • No Loud Music

  • Observe Start and Stop Times

  • Leave it the Way You Found it

  • Dress Like a Professional

  • Hydrate!

Click the buttons below to view site plans, schedules etc. throughout the week.