Paver Driveway & Back Patio Steps
DAY 1 OBJECTIVES:
Customer: Christie & Dan Phillips
Address: 1502 Covered Bridge Dr. (DeLand, FL)
Crew:
(DM) Eric Moore
(CM) Christian Myers
Sub: Silvano (SMR PAVERS)
Sub: Gel Corps (Live Loading)
Tuesday Morning: Cam & Nate to aid
SCOPE:
(Prep)
DEMO of driveway to be completed by McBride, Followed by grading to prep for paver base:
On Site (20 yd.) Dumpster to be delivered to site btween 8:30-9:00 am.
Live Load Process to begin between 10:30-11:00 am
While we wait for the first live load truck to arrive Eric is to begin peeling up concrete slabs utilizing big skid and breaking apart by ground crew as needed with sledge hammers.
Place all large slabs at the beginning of the driveway to prep for live load in live load area designated on site plan 1.0
Demo of driveway and grading is to be completed by the end of the day
(Pavers) - Silvano (SMR Pavers for Install)
24 Pallets of Tremron Pavers Delivered to site on 6/19 Received by Nathan:
Monday: 9:00 am (13) Pallets Delivery
Tuesday: 8:30 (11) Pallets Delivery
Placed in loading zones on RH & LH Sides of Lawn
Silvano to coordinate Paver Base Delivery for Wednesday Morning
Silvano To install the paver base and pavers in Herringbone Style Pattern Pictured Below
Silvano to recycle front walkway pavers to build steps at back patio (Site Plan 2.2)
Equipment:
7.3 with Dovetail and Big Skid with all attachments.
Sledgehammers (However many we have at the shop and in the rigs).
Backpack Blower.